Mayfield Road - Wiseman's Creek Crossing Construction

The final concrete pour for the new crossing over Wiseman’s Creek has been completed. Work on construction of the road approaches to the new crossing has commenced.  We expect to complete this work in the next two weeks in readiness for bitumen sealing, however sealing will not be carried out until weather conditions improve.  Guardrail will also be installed prior to opening up to traffic.