Fixing Local Roads Grant (Round 1) Works - Campbell's River Road

The Campbell’s River Road project under Fixing local Road grant (round 1) has recommenced recently on Monday 25th October.

Primary stage work involves 200 mm gravel overlay, shoulder widening, maintaining table drain, etc., followed by mixing with stabilising agent Slag and lime for structural integrity of the pavement.

In the first week, productivity was high with over 1060m completed in 5 days. It is anticipated the stabilisation work will be completed by mid November subject to favourable weather conditions.